2165 – CONVEYOR BELTS FOR SPOIL SYSTEM IN THE TUNNEL OF THE GAS PIPELINE (LENGTH 1.200m) ON MOUNT CUCCHERO

SOLUTION FOR BULK MATERIALS

Design, supply and commissioning of a belt conveyor system for the spoil removal of the Monte Cucchero tunnel excavated TBM full-section milling machine LOVAT RMP167SE.

The transport line has been developed in a tunnel for over 1,200m, with a downhill path. The stopping time is about 10 seconds.

JOB NUMBER
2165

SECTOR
TUNNELING

END USER
SNAM RETE GAS

LOCATION
ITALY

YEAR
2002-2003

CUSTOMER
SOCIETÀ ITALIANA PER CONDOTTE D’ACQUA s.p.a.